Umm Al Nar Power Station

Umm Al Nar Power Station

Project Summary

Service: Site Services

Duration: 4 Weeks

 

Background

Quartzelec successfully completed the onsite inspection and major overhaul of steam turbine and generator 11 at Umm Al Nar Power Station and Desalination Plant in Abu Dhabi. The machine – a 386MVA Toshiba TAKS machine, was originally installed in 2004.

The Project

Operator ITM O & M Company Ltd awarded the £275,000 contract to Quartzelec as the result of a competitive tender process.

The hydrogen cooled machine was inspected by a team of Quartzelec Abu Dhabi engineers with the additional support of site engineers from Quartzelec’s Rugby facility to assist with the additional responsibility of overseeing the turbine works.

 CS46

 